Major environmental protection investments at a glance

And our employees are also highly motivated: Since 1998, they have made 243 improvement suggestions for environmental protection, 225 of which were implemented. External environmental protection auditors have attested to our more than average commitment in the area of environmental protection for many years.

2024

 
Annual investment: 844,364 €

 

2022

  • Drip pan for recycling centre
  • Charging facility for electric cars
  • LED lighting
  • IT module for paperless logistics department

2021

  • Photovoltaic system 413 kWp
  • Sprinkler system in logistics centre
  • Renewal of roof with heat insulation in plastic injection moulding and tool design building
  • 2020
  • LED lighting in plastic injection moulding building for teams 1 and 2
  • Automatic window control for optimised ventilation for teams 3 to 6
  • Installation of fire alarm system in the plastic injection moulding plant, assembly, logistics, laboratory and technology
 
Annual investment: 778,970 €

 

2020

 
Annual investment: 347,100 €

 

2019

  • LED lighting for assembly 1, stationary gas analysis and tool design
  • New water treatment for cooling water in the plastic injection moulding plant
  • Replacement of heating circuit pumps with energy-saving pumpsn
 
Annual investment: 29,950 €

 

2018

  • Fire alarm system in the production area
  • LED lighting for car park area of administration department
  • New compressed air system in assembly
 
Annual investment: 48,500 €

 

2017

  • Reduced paper consumption thanks to SAP
  • LED lighting in the technical building and canteen warehouse
  • Replacement of pneumatic screwdrivers by electric screwdrivers
  • Fire protection panels in the forklift charging area
  • Technical overhaul of fire protection doors
 
Annual investment: 44,700 €

 

2016

  • LED lighting for goods receipt, dispatch, technology and outdoor facilities
  • Circulation system for test bench for temperature changes
  • Full renewal of the compressed air lines in the assembly area
  • Replacement of pneumatic screwdrivers by electric screwdrivers
 
Annual investment: 56,300 €

 

2015

  • Energy audit DIN EN 16247-1
  • New insulated glazing windows in service department
  • Conversion of the operating instructions to a new format
  • Conversion to LED lighting in various areas
 
Annual investment: 70,000 €

 

2014

  • Study "Energy Efficiency"
  • Solar thermal energy system for service water
  • Photovoltaic system 105 kWp
  • Conversion to LED lighting in passageways and outdoor areas
 
Annual investment: 133,840 €

 

2013

  • Underfloor heating system in new training room
  • Rainwater cistern 20,400 litres
  • Conversion of lighting in preproduction (new light colour with mirror -> 50% energy saving)
  • Two permanently installed measuring systems for measurement of consumption of compressed air
  • Measuring system for measuring and optimising the energy consumption of plastic injection moulding machines
  • Measuring system for detecting compressed air leaks
 
Annual investment: 32,260 €

 

2012

  • Tightness test of all wastewater pipes
  • Hydraulic balancing of the entire heating system with Vario-Q valves
  • Insulated glazing windows in the intermediate building of the production hall
 
Annual investment: 28,550 €

 

2011

  • Downhole heat exchangers
  • Underfloor heating system Lindenstraße 33
  • Glazed entrance elements Administration
  • Fire protection measures
  • Fire alarm system laboratory and technology
 
Annual investment: 140,015 €

 

2010

  • Photovoltaic system 61 kWp
  • Fire protection door
  • Gas analyser for containers
  • Outdoor silo for granular plastics
  • Partition wall in goods receipt
  • Heat insulation of facade of assembly hall
 
Annual investment: 180,959 €

 

2009

  • Photovoltaic system 171 kWp
  • New windows in the staircase
  • New roof with heat insulation in Amorbach
 
Annual investment: 649,621 €

 

2008

  • New roofs and windows for technology and administration buildings
  • Heat insulation of facade of administration building
  • New insulated heating pipes between brick building and technology building
  • Solar system for hot water on the roof of the plastic injection moulding plant
  • Smoke and heat extraction system in staircase of administration and technology buildings
  • New compensation system in transformer station plastic injection moulding plant
  • Fire protection measures
 
Annual investment: 244,189 €

 

2007

  • Redesign and recultivation of the outdoor areas
  • Flood protection in the area of the production hall
  • Smoke protection and smoke detectors in the tool store II

2006

  • Replacement of single glazing by insulating glazing in the "tools and equipment making" hall
  • Replacement of all basement windows by windows with insulating glazing
  • Reporting the water levels of the Zaber river with the web-based event reporting system EMS 442
  • Replacement of powder extinguishers by foam extinguishers

2005

  • Flood protection through earthmoving along the course of a brook
  • Flood protection with sheet piling retaining walls at all doors and gates at risk
  • Installation of surveillance cameras at recycling centre

2004

  • Heating of the office extension through heat recovery from the compressor system
  • Replacement of the cooling tower by a closed circuit cooling system for the plastic injection moulding plant

2003

  • Expansion of the fire extinguishing system
  • Energy savings with new granulate dryers

2002

  • High-speed doors in the production halls
  • Saving paper through electronic archiving
  • Reduced water consumption due to installation of a recirculation system for laboratory tests